Japan’s Mid-Long Term Market design takes shape

Publication date: Sept 1, 2026  Key Takeaways Japan is moving toward longer-term electricity procurement, with proposed obligations requiring retailers to secure 50% of expected demand three years ahead and 70% one year ahead. A new Mid-Long Term Market is expected to begin in FY2028 to support this shift. Retailers will be able to meet these …

Tighter Grid Connection Rules for Low-Voltage BESS and Large-Scale Demand

Publication date: Aug 10, 2026  Tighter Grid Connection Rules for Low-Voltage BESS and Large-Scale Demand The Ministry of Economy, Trade and Industry (METI) presented plans at an expert meeting to extend stricter grid connection rules to low-voltage grid-scale BESS facilities. METI has already introduced measures for generation facilities, including BESS facilities connected at high voltage …