Shulman Advisory

Japan Data Center Update 45: Japan Explores New Ways to Power and Site Data Centers

Publication date: Nov 25, 2026 

Japan Data Center Update 45: Japan Explores New Ways to Power and Site Data Centers

METI considers faster grid connections for data centers that accept power restrictions

A new framework is under development to connect large electricity users such as data centers to the grid sooner, as a rise in connection requests has lengthened wait times in some regions. The Ministry of Economy, Trade and Industry (METI) is considering allowing earlier connections on the condition that facilities accept limits on their power draw when, for example, power flows exceed a transmission line’s operating capacity. The proposed framework would apply nationwide to customers with demand of 30 MW or more connecting to the extra-high-voltage grid. Customers would generally be expected to cover costs such as installing equipment that can cut power to their facilities.

Hokkaido urges early LNG power development and priority support for floating offshore wind to host data centers

Hokkaido Governor Naomichi Suzuki met with Kei Takagi, State Minister of Economy, Trade and Industry, and presented a written request as the government develops its Power GX (Green Transformation) strategy. To avoid missing out on investment from large electricity users such as data center operators, the request called for early development of LNG-fired power plants during the transition period while offshore wind projects advance. It specifically sought support for transmission grid and LNG-fired power development. Suzuki also urged the government to designate southern Hokkaido as a priority area for floating offshore wind and prioritize efforts to create favorable conditions for project development there.

Hokkaido Electric is considering building an LNG-fired power plant on a site adjacent to its thermal power station (Original Source: Nikkei).

Cosmo Energy and Gunma University to test edge data centers at former gas stations

Cosmo Energy Holdings and Gunma University will test edge data centers at former gas station sites in Gunma Prefecture from November through September 2027. This will be Japan’s first edge data center pilot to use sites owned by an energy company. Edge data centers are small facilities that process data close to where it is generated and place less strain on the power system than large urban data centers. Cosmo Energy plans to use operating gas stations, former station sites, and idle land across Japan.

–